Gantt Chart and Work Breakdown Structure Engineering Essay (Other (Not Listed) Sample)

Instructions:

Develop a work breakdown structure for ACME HOME IMPROVEMENTS DE MÉXICO, SA DE CV

source..
Content:

IDTask
Mode
Task NameDurationStart
April 2016May 2016June 2016July 2016
111417202326291471013161922252814710131619222528313691215 18 21 24 27 30 3 6 9
1 Start318 daysFri 3/18/16
2 ACME HOME
IMPROVEMENTS DE MÉXICO, SA DE CV
318 daysFri 3/18/16
1 Feasibility7 daysFri 3/18/16
2 Risk Analysis 7 daysFri 3/18/16
Quantity Surveyor
3 Project
Breakeven Analysis
4 Planning and
Design
5 daysFri 3/18/16
21 daysFri 3/18/16
Accountant
1 Statement of 21 daysFri 3/18/16 work
2 Structural 14 daysFri 3/18/16
3 Electrical14 daysFri 3/18/16
Structural Eng. ELectrical Eng.
4 Obtaining
site
5 Work
Schedule and Cost
6 Work
Schedule
7 Cost
estimate
8 Preparation
of Technical Drawings
21 daysFri 3/18/16
14 daysFri 4/15/16
3 daysFri 4/15/16
14 daysFri 4/15/16
14 daysFri 3/18/16
Client
Contractor Qs.
Design Team
Client
Client/Contractor Qs'
15Customer Approval2 daysWed 4/6/1616Stage Permit14 daysMon 4/18/1617Application of Permit1 dayMon 4/18/1618Approval by Authority14 daysMon 4/18/1619Construction/B220 daysFri 5/6/1620Site Clearanc1 dayFri 5/6/1621Dismantle Existing Structures1 dayFri 5/6/1622Clear site of all bushes, arising and1 dayFri 5/6/16Client Project Management Team
uLocal Authority
Manual Laborers
Manual Laborers
Project: MS Project Assignment Date: Tue 8/13/19
Task Split
Milestone Summary Project Summary
Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only
Manual Summary Rollup Manual Summary
Start-only Finish-only External Tasks
Page 1
External Milestone Deadline
Critical Critical Split Progress
Manual Progress
IDTask
Mode
Task NameDurationStart
April 2016May 2016June 2016July 2016
111417202326291471013161922252814710131619222528313691215 18 21 24 27 30 3 6 9
24Deliver Materials To Site1 dayFri 5/6/1625Lay14 daysMon 5/9/16Foundation26Build the180 daysMonwalls, floor6/13/16and roof ofthe27Install7 daysMonelectrical2/20/17andplumbingfixtures28Finish7 daysWed 3/1/17interiorand stockinventory29Services40 daysMonand5/23/1632Adjoining20 daysFri 5/6/16Structuresand Services33Build the14 daysFri 5/6/16garage34Complete all14 daysFri 5/6/16paving andlandscaping35Internal2 daysFri 3/10/17Qualification36QA/QC Check2 daysFri 3/10/1737Internal2 daysFri 3/10/17Inspection38Customer60 daysTue 3/14/17Acceptance39Inspection1 dayTue 3/14/17with Town40Customer1 dayTue 3/14/17Acceptance41Handover1 dayTue 3/14/1742Hire and train60 daysTue 3/14/17employees43Finish0 daysTue 6/6/1723Building220 daysFri 5/6/16
Materials Supplier
Contractor
Contractor
Mechanical subcontractor
Project: MS Project Assignment Date: Tue 8/13/19
Task Split
Milestone Summary Project Summary
Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only
Manual Summary Rollup Manual Summary
Start-only Finish-only External Tasks
Page 2
External Milestone Deadline
Critical Critical Split Progress
Manual Progress
August 2016

September 2016

October 2016





November 2016





December 2016







J

12

15

18

21

24

27

...
Get the Whole Paper!
Not exactly what you need?
Do you need a custom essay? Order right now:

Other Topics:

  • Portal Frame Construction: Technique Of Designing And Constructing
    Description: Portal frame construction refers to the technique of designing and constructing structures, whereby two-dimensional rigid frames with basic characteristics of the rigid joint are between the beam and the column are utilized....
    17 pages/≈4675 words| No Sources | Other | Engineering | Other (Not Listed) |
Need a Custom Essay Written?
First time 15% Discount!